- Door Entry Awning
Door Entry Awning
Door Entry Awning - Construction - Early Start discount - March Start/Finish
- Demolition Phase 1. All White trim, front siding and make access for 2by lumber.
- Demolition Phase 2. Add framing lumber, frame roof and add all new plywood sheets
- Add Flashing and caulk, roofing underlayment and shingles
- Add marine grade plywood to front and add cedar shake shingles to new front.
- Trim work Crown molding to match. Caulk, Sand and Paint Exterior White
- Measure for corbels. Build, Paint and add to front face. Trim touch ups.
Hand Rail TBD
Schedule: To reserve this job, weather permitting we will schedule time.
*Demolition Phase 1 March 8 or 11 (Save $500) ............ $1250 (Pay by 2/15)
*Demolition Construction Phase 2 March 16 (Save $500).. $1000 (Pay by 3/15)
Add Flashing caulk - shingles March 18 ......................... $ 950
Add plywood & trim March 30 ...................................... $ 950
TOTAL ...........(Save $1000 if we start and finish) .....$3,900.00
FENCE REMOVE and REPLACE new Painted 3 New posts cemented.
Cost...............................................................................$600.00
*2-15 Payment will guarantee a timely start and finish.
We are booking projects for March and April.